Nedpower Mt Storm Project Illegal Turbine sitings diagrams

The Nedpower project seems to be managed with complete distain for people's rights and for federal regulations.

The latest findings are that three turbines located at the intersection of the Grass Ridge road and the local access road shown above are almost certainly within 800 ft of at least one residence. As shown in the map diagram above.

The map shows the sitings involved and the photograph below shows the construction occurring of the upper two turbines.
The impact of turbines this close to peoples homes is likely to be devastating on their living conditions - see report and real peoples experiences here.

Once again Nedpower's claim to be a "Good Neighbor in Grant County" that misled the WV PSC in their original decision is looking completely transparent. When given an entire mountain top on which to site turbines - they immediately choose locations that are cheapest for them - namely directly next to existing roads and properties. Instead of trying to minimize the impact on residents, that is the last thought on their engineers minds. In fact given the blatant siting of these turbines - the engineers have clearly been given carte blanche to disregard any aspects relating to impacts either human or environmental.
Notice all these turbines are within a few hundred feet or less of the roads themselves.

Nedpower were obviously also counting on the nuisance law suit against them to be dismissed. Instead the case is back in court and Nedpower now have to answer not only nuisance charges but also illegal siting charges.

View of the turbines located adjacent to Grassridge Road, looking down the hill from the corner of the access road:

1 Comments:

At 4:47 AM, Blogger windbusters said...

TO ANY ONE WHO IS INTERESTED IN INFO ON GAMESA IN PA.
WE SPENT LAST WEEKEND SCOPING OUT GAMESAS WIND FARM ON MT. LILLY IN PORTAGE PA. THIS IS THE SITE WHERE THE BLADE FRAGMENTATION OCCURED IN LATE MARCH OF THIS YEAR.
WE ALSO HAVE PHOTOS OF THE BROKEN BLADES WHICH ARE NOW LOCATED AT THIER ENDENSBURG,PA. PLANT.
WE ALSO HAVE ADDITIONAL INFO IF ANYONE IS INTERESTED.
OUR MISSION IS TO INFORM RESIDENTS AFFECTED IN PA. AND TO PROVIDE THEM WITH THE RULES AND REGS. THAT APPLY SO THER IS AN EVEN PLAYING FIELD. WE CAN NOT PROTECT OUR RIGHTS IF WE DO NOT KNOW THEM. NEVER ALLOW ANYONE TO TAKE YOUR RIGHTS AWAY.
RESPECTFULLY,
JUDI PICCOLELLA

 