Kittitas County, WA - Judge rules on cancelled EnXco wind power project
Judge Cooper’s 11-page ruling stated commissioners had good reason to deny the project because it conflicted with neighboring properties and how those lands are being used.
“There is ample evidence in the record to support the finding that the project does not bear a substantial relationship to the public health, safety or welfare and is incompatible with uses in the area.”
Ed Garrett - local citizens advocacy group spokesman said - “Wind farm developers have proven themselves to be the kind of unethical developers that this county does not need.”
County commissioners on April 5 denied permits requested by EnXco USA Inc. for the French-based company’s planned 120-turbine wind farm eight miles north of Ellensburg. The company later filed an appeal in county Superior Court. A hearing on the appeal took place Oct. 6.
The full text can be viewed here.